Type: Private Cable

Common Carrier: No

Owners: Docomo Pacific

Cost: $26 m

Builder: NEC

Equipment Supplier: Ciena

Distance: 279 km

Segments:

 Segment 1: Tata Piti CLS to Rota branching unit.

 Segment 2: Rota branching unit to new CLS at Songsong Village, Sasanlagu, Rota (land owned by CNMI Govt)

 Segment 3: Rota branching unit to Tinian branching unit.

 Segment 4: Tinian branching unit to CLS at Tachognya Beach, Tinian (land owned by CNMI Govt)

 Segment 5: Tinian branching unit to existing Docomo Pacific structure at Sugar Dock South, Saipan. (land owned by M.S. Villagomez, Inc.)

 Trunk is Segments 1, 3, and 5. Three fibre pairs, 100 Gbps lit. Remaining local routes will be lit at 10 Gbps.

Total Capacity: 7,200 Gbps

Lit Capacity: 200 Gbps

Landing Points: Aquarius Beach, Saipan

Ready for Service: 14 June, 2017

Links:

https://www.ciena.com/about/newsroom/press-releases/DOCOMO-PACIFIC-announces-ATISA-Submarine-Cable-System-Ready-for-Service.html

https://www.subcableworld.com/newsfeed/fiber-optic-cables/docomo-pacific-starts-marine-lay-of-atisa-cable-in-the-mariana-islands

https://www.guampdn.com/story/money/2017/05/05/docomo-pacifics-atisa-undersea-cable-project-connect-guam-saipan-tinian-rota/101318252/